Ballintaggart and Ballybricken townlands Ringaskiddy Co. Cork
CONDITIONALPlanning application 21/4631
Cork - Cork County Council
Proposed Development
A 10 year planning permission to amend the recently permitted development for the construction of a contractor’s compound, welfare facilities, an internal access road and associated works, Ref: 20/5533. The amendments include adjusting internal access roads and associated works. The proposed amendments include relocating a section of road accessing the permitted contractors compound, construction of associated earth reinforced retaining walls, the working and grading of site-won material, the removal of 88 trees, replacement planting of 90 trees, the erection of protective fencing around trees that are to remain, and some other minor demolitions and alterations. The proposal includes the removal of 3 No. double-stacked temporary portable contractor cabins (total floor area removed = 192m2, overall height of 4.95m) and removal of a section of steel gantry walkways from the previously permitted contractors compound. The development will include all adjustments required to associated on-site infrastructure. The proposed development is covered by an existing Industrial Emissions Directive Licence No. P0013-04. As the development refers to a modification to an establishment to which the Major Accident Directive applies information as specified in the third schedule of the Major Accident Regulations will be submitted with the application.
View the full application file on the council's planning portal →Application Timeline
Application received
11 Mar 2021
Decision: CONDITIONAL
31 May 2021
Decision due
3 Jun 2021
Grant issued
6 Jul 2021
Application Details
- Location
- Ballintaggart and Ballybricken townlands Ringaskiddy Co. Cork
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 11 March 2021
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 31 May 2021
- Grant Date
- 6 July 2021
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
A 10 year planning permission to amend the recently permitted development for the construction of a contractor’s compound, welfare facilities, an internal access road and associated works, Ref: 20/5533. The amendments include adjusting internal access roads and associated works. The proposed amendments include relocating a section of road accessing the permitted contractors compound, construction of associated earth reinforced retaining walls, the working and grading of site-won material, the removal of 88 trees, replacement planting of 90 trees, the erection of protective fencing around trees that are to remain, and some other minor demolitions and alterations. The proposal includes the removal of 3 No. double-stacked temporary portable contractor cabins (total floor area removed = 192m2, overall height of 4.95m) and removal of a section of steel gantry walkways from the previously permitted contractors compound. The development will include all adjustments required to associated on-site infrastructure. The proposed development is covered by an existing Industrial Emissions Directive Licence No. P0013-04. As the development refers to a modification to an establishment to which the Major Accident Directive applies information as specified in the third schedule of the Major Accident Regulations will be submitted with the application.
Ballintaggart and Ballybricken townlands Ringaskiddy Co. Cork
Partial demolition of a redundant waste water treatment plant comprising the demolition of a concrete Aeration Basin, two concrete Clarifiers, two steel effluent holding tanks, an Air Blower House and all associated plant, equipment and site works. The proposed development is covered by an existing Industrial Emission Licence No. P0013-04. The development refers to a modification to an establishment to which the Major Accident directive applies.
Ballintaggart and Ballybricken Ringaskiddy Co. Cork
Permission for the works will include demolition of a section of existing stormwater outfall pipe with associated concrete encasement and the construction of a replacement section of stormwater outfall pipe with an additional discharge point and associated concrete encasement. The construction will also include associated site works consisting of minor site clearance, excavation works and temporary works. The proposed development is covered by an existing Industrial Emissions Licence no. P0864-01. A Natura Impact Statement (NIS) will be submitted to the planning authority with the application.
Ballintaggart, Shanbally, Ringaskiddy, Co. Cork, P43R298
Erection of 2.4m high security fencing and low level barriers to parts of boundary
API Plant Ballintaggart Ballybricken Ringaskiddy
A 10 year permission for the construction of a new Clinical Manufacturing Facility (referred to as RCMF) at the existing Pfizer site. The proposed RCMF facility will include (i) a new five storey clinical manufacturing building (c.11,468sqm and maximum height 29.425m) which will include production areas, laboratories, ancillary office space, warehouse, and plant and utility space. The building will be constructed in two sequential phases, Phase 1 comprising c.9,465 sqm and Phase 2 comprising c.2,003sqm; (ii) a single storey warehouse drum store building (c.420sqm and maximum height 13.00m); (iii) an external utility yard comprising; a two storey electrical building (c.94sqm and maximum height 11.70m), an emergency generator with flue stack, 1No. liquid nitrogen tank, 2No. evaporators, 3No. bunded chillers, 2No. bunded receiver tanks, 2No. bunded glycol tanks, a three storey steel frame structure (to a maximum height of 12.91m) to accommodate; dry coolers, heat exchangers and other miscellaneous utility plant and machinery above the utility yard; (iv) an elevated structural steel piperack (c.210m in length and maximum height 9.19m) to provide piped utility services to the new facility, and; (v) all associated site development works, including roads, paths, yards, underground services and landscaping. This application relates to development which comprises an activity which holds an Industrial Emissions Directive Licence (P0013-04). As the development refers to a modification to an establishment to which the Major Accident Directive applies, information as specified in the third schedule of the Major Accident Regulations will be submitted with the application. An Environmental Impact Assessment Report (EIAR) and a Natura Impact Statement (NIS) have been prepared and will be submitted to the Planning Authority with the application.
The existing Pfizer site in Ballintaggart and Ballybricken Ringaskiddy Co. Cork
A 10 year planning permission for the construction of a contractor’s compound, welfare facilities, an internal access road and associated works. The proposed compound will be built in the area previously occupied by the ADM waste water treatment plant, which is currently being demolished, Planning Ref. 18/6631 relates to this demolition. Part of the aeration basin tank walls which were to be demolished under Planning Ref. 18/6631 will now be retained as part of this proposed development. Enabling works will include the demolition of the former ADM workshop and stores (total floor area = 820m2 with an overall height of 8.12m): Demolition of this building was previously permitted as part of the expired planning application 12/5768, the relocation and grading of site – won material, the removal of 91 trees, protective fencing around trees that are to remain, and some other minor demolitions and alterations. The proposed development will include: A two-storey canteen and meeting rooms building (total floor area = 337m2 with an overall height of 6.45m); a toilet and shower building (total floor area = 202m2 with an overall height of 3.15m); an electrical sub-station ( total floor area = 56m2 with an overall height of 3.15m); a pickling shed (total floor area = 92m2 with an overall height of 4.74m); double-stacked temporary portable contractor cabin (total floor area = 808m2 with an overall height of 4.95m); steel gantry walkways and stairs: a workshop and storage containers area (total floor area = 1290m2 with an overall height of 2.45m); a waste and recycling area for accommodating skips; a laydown area; a new security building (total floor area = 66m2 with an overall height of 3.15m); new internal roads, footpaths and set-down area, relocation of existing car parking spaces and provision of an additional 20 parking spaces, new car park information sign board at the site entrance. The development will include all associated on-site infrastructure. The proposed development is covered by an existing Industrial Emissions Directive Licence No. P0013-04. As the development refers to a modification to an establishment to which the Major Accident Directive applies information as specified in the third schedule of the Major Accident Regulations will be submitted with the application.
Ballintaggart Ringaskiddy Co. Cork
Retention of 60m high 300mm diameter steel mast mounted with instruments to collect meteorological data
Ballintaggart Ringaskiddy
Retention of a 60m high 300mm diameter steel mast mounted with instruments to collect meteorological data
Ballintaggart Ringaskiddy
Permission for the construction of a guardhouse building and associated works, including; canopy, ramp, concrete plaza, local internal access road widening, fencing, external lighting, drainage and footpaths. An existing permitted storage shed will also be kept on site indefinitely (currently subject to permission to demolish as part of planning reference 20/5533). The proposed development is covered by an Industrial Emissions Directive Licence no. P0013-05. As the development refers to a modification to an establishment to which the Major Accident Directive applies, information as specified in the third schedule of the Major Accidents Regulations will be submitted with the application
Ballintaggart & Ballybricken Ringaskiddy Co.Cork
The works will include (1) A 4-storey extension to the east of the existing manufacturing building, (2) A 2-storey extension to the north of the existing warehouse, (3) relocation of the existing eastern car park and rationalisation and relocation of the previously granted car park spaces (Planning Reg. Nos. 15/5818 and 17/5791) to a proposed new site car park to the west of the existing manufacturing building, (4) A single storey extension to the south of the existing warehouse to support warehouse operations and (5) part demolition of the existing temporary modular building (Planning Reg. No. 14/5337) to facilitate construction works and the erection of a new temporary modular building to the east of the existing manufacturing building for office use with link into the part-demolished existing modular building. The construction will also include associated site development works including internal roads and drainage. The proposed development is covered by an existing Industrial Emissions License No. P0864-01.