Proposed Development
The construction of a warehouse building for storage, distribution and manufacturing, with ancillary 2-storey offices, staff facilities, parking, entrance off existing public road and all associated site works.
Application Timeline
Application received
27 May 2021
Decision due
26 Oct 2021
Decision: CONDITIONAL
27 Oct 2021
Grant issued
2 Dec 2021
Application Details
- Location
- Barnahely Ringaskiddy Co. Cork
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Cork County Council
Timeline
- Registration Date
- 27 May 2021
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 27 October 2021
- Grant Date
- 2 December 2021
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
Stainless steel frame smoking shelter perimeter fencing and associated ancillary site works at existing facility. The facility is subject to an Integrated Pollution Prevention and Control Licence.
Barnahely Ringaskiddy Co. Cork
Erection of 25m support pole carrying 3 no. 2.8m radio aerials for use by The Emergency Services with associated equipment for new National Digital Radio Service
Eircom Exchange Barnahely Ringaskiddy
Relocation of existing stone boundary wall on IDA property adjacent to the access road to the Janssen Biologics manufacturing facility and re-grading of the embankment between the new wall location and the R613 roadway to provide enhanced sightlines for the access road to the facility
Barnahely Ringaskiddy Co.Cork
Extending the existing car park by 96 spaces, comprising of new dense bitumen macadam surface, additional footpaths, smoking shelter, lighting, drainage and all associated site works. This application relates to development which comprises of an activity whcih requires an integrated pollution prevention and control licence.
Barnahely Ballybricken Ringaskiddy
Construction of additional pre-fabricated single storey offices
Barnahely Ringaskiddy
Retention of 2 no. temporary prefabricated extensions to existing facility for use as offices and engineering laboratory
BARNAHELY, BARNAHELY,
Permission for one wind turbine only, to be located on the northern portion of the application site. Extension of Duration to Permission granted under Planning Ref. No. 11/4946; ABP ref 04.240330
Raheens Barnahely Shanbally, Ringaskiddy Co.Cork
Erection of 2 no. wind turbines with hub height of up to 100m, blade radius of up to 50.5m and overall height from ground to tip of blade of up to 150.5m, upgrade of existing site roads, construction of internal site tracks and all other associated works
Raheens Barnahely Shanbally Ringaskiddy
Permission for 1 No. prefabricated single storey building for manufacturing installed to the north east of the site and with link corridors to be provided from proposed building to existing buildings, Planning Permission for Retention for 4 no. single storey prefabricated buildings uses as following: No.1 Circuit Board Testing ( Previously permitted under 03/403, No.2 Locker room, No.3 Storage and No. 4 Office/Training Room (Previously permitted under 06/10613), all with links to main building and Retention of extension to existing carpark with 34 additional parking spaces and all associated site works.
Barnahely, Ringaskiddy, Co. Cork, P43HD42
Permission for 1 no. prefabricated single storey building for manufacturing installed to the north east of the site and with link corridors to be provided from proposed building to existing buildings, planning permission for retention for 4 no. single storey prefabricated buildings uses as follows; no.1 circuit board testing (previously permitted under 03/403), no. 2 locker room, no.3 storage and no. 4 office/training room (previously permitted under 06/10613), all with links to main building and retention of extension to existing carpark with 34 additional parking spaces and all associated site works