A c. 1.82 Ha site at Summerhill , Portlaoise , Co. Laois
N/APlanning application 2560379
Laois - Laois County Council
Proposed Development
develop Phase 4 of the wider Sand Wood Development, (generally bound by: the Southern Circular Road and Aghnaharna Drive to the north; the Holy Family Schools and Ashewood Walk to the east; and agricultural land to the south and west). Phases 1A & 1B (permitted under LCC Reg. Ref. 23/60350 & 23/60348) are currently under construction and applications for Phases 2 & 3 are submitted alongside this Phase 4 application. The Phase 4 site is generally bound by: the Holy Family Schools to the north; Ashewood Walk residential estate and agricultural lands to the east; and agricultural lands to the west (proposed Phase 3) and south. The development will principally consist of the provision of 36 No. 4-bed, 2 No. storey houses. The development will also include: the continuation of the Link Road permitted in Phases 1A & 1B, as proposed to be amended as part of the Phase 2 application and extended as part of the Phase 2 & 3 applications; car parking; public open space; drainage connections; boundary treatments; hard and soft landscaping; lighting; and all associated site and development works above and below ground
Application Details
- Location
- A c. 1.82 Ha site at Summerhill , Portlaoise , Co. Laois
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Laois County Council
- Site Area
- 1.82 ha
Timeline
- Registration Date
- 26 June 2025
- Status
- INCOMPLETED APPLICATION
- Decision
- N/A
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
provide 36 No. 4-bed, 2 No. storey houses.The development will also include: the continuation of the Link Road permitted in Phases 1A & 1B, as proposed to be amended as part of the Phase 2 application and extended as part of the Phase 2 & 3 applications; car parking; public open space; drainage connections; boundary treatments; hard and soft landscaping; lighting; and all associated site and development works above and below ground.
A c. 1.82 Ha site at Summerhill , Portlaoise , Co. Laois
develop Phase 3 of the wider Sand Wood Development, (generally bound by: the Southern Circular Road and Aghnaharna Drive to the north; the Holy Family Schools and Ashewood Walk to the east; and agricultural land to the south and west). Phases 1A & 1B (permitted under LCC Reg. Ref. 23/60350 & 23/60348) are currently under construction and applications for Phases 2 & 4 are submitted alongside this Phase 3 application. The Phase 3 site is generally bound by: Phases 1A & 1B to the north; the Holy Family Schools and agricultural lands (proposed Phase 4) to the east; and agricultural lands to the west (part of which represents the proposed Phase 2) and south. The development will principally consist of the provision of a creche (c. 961 sq m) and 74 No. residential dwellings comprising 64 No. 4-bed houses and 4 No. 1-bed and 6 No. 2-bed sheltered housing units. The proposed development will be 1 No. and 2 No. storeys in height. The development will also include: minor amendments to the landscape and boundary treatment to the south of the Phase 1A site to provide car parking and access to the proposed creche; the continuation of the Link Road permitted in Phases 1A & 1B, as proposed to be amended and extended as part of the Phase 2 application; car parking; cycle parking; public open space; drainage connections; boundary treatments; hard and soft landscaping; lighting; and all associated site and development works above and below ground.
A c. 4.15 Ha site at Summerhill , Portlaoise , Co. Laois
construct a creche (c. 961 sq m) and 74 No. residential dwellings comprising 64 No. 4-bed houses and 4 No. 1-bed and 6 No. 2-bed sheltered housing units. The proposed development will be 1 No. and 2 No. storeys in height. The development will also include: minor amendments to the landscape and boundary treatment to the south of the Phase 1A site to provide car parking and access to the proposed creche; the continuation of the Link Road permitted in Phases 1A & 1B, as proposed to be amended and extended as part of the Phase 2 application; car parking; cycle parking; public open space; drainage connections; boundary treatments; hard and soft landscaping; lighting; and all associated site and development works above and below ground.
A c. 4.15 Ha site at Summerhill , Portlaoise , Co. Laois
extension of duration for planning ref. 08/151
Summerhill or Aghnaharna and Ballymoney , Portlaoise.
develop Phase 2 of the wider Sand Wood Development (generally bound by: the Southern Circular Road and Aghnaharna Drive to the north; the Holy Family Schools and Ashewood Walk to the east; and agricultural land to the south and west). Phases 1A & 1B (permitted under LCC Reg. Ref. 23/60350 & 23/60348) are currently under construction and applications for Phases 3 & 4 are submitted alongside this Phase 2 application. The Phase 2 site is generally bound by Phases 1A & 1B to the north and agricultural lands to the east (proposed Phase 3), south and west. The development will principally consist of the provision of 92 No. residential dwellings comprising 86 No. 4-bed houses and 6 No. 2-bed sheltered housing units. The proposed development will be 1 No. and 2 No. storeys in height. The development will also include: minor amendments to the Link Road permitted as part of Phases 1A & 1B and its continuation through the Phase 2 site; minor amendments to the landscape and boundary treatment to the south of the Phase 1A site; car parking; cycle parking; public open space; drainage connections; boundary treatments; hard and soft landscaping; pumping station; lighting; and all associated site and development works above and below ground
A c. 3.85 Ha site at Summerhill , Portlaoise , Co. Laois
construct 92 No. residential dwellings comprising 86 No. 4-bed houses and 6 No. 2-bed sheltered housing units. The proposed development will be 1 No. and 2 No. storeys in height. The development will also include: minor amendments to the Link Road permitted as part of Phases 1A & 1B and its continuation through the Phase 2 site; minor amendments to the landscape and boundary treatment to the south of the Phase 1A site; car parking; cycle parking; public open space; drainage connections; boundary treatments; hard and soft landscaping; pumping station; lighting; and all associated site and development works above and below ground.
A c. 3.85 Ha site at Summerhill , Portlaoise , Co. Laois
retain amendments to 7 No. houses permitted as part of the residential development granted under LCC Reg. Ref. 25/60385 at a c. 3.85 Ha site at Summerhill, Portlaoise, Co. Laois. This application relates to Phase 2 of the wider Sand Wood Development (generally bound by: the Southern Circular Road and Aghnaharna Drive to the north; the Holy Family Schools and Ashewood Walk to the east; and agricultural land to the south and west). The Phase 2 site is generally bound by: agricultural lands to the west; Phases 1A & 1B (permitted under LCC Reg. Refs. 23/60350 & 23/60348, as amended under LCC Reg. Ref. 25/60040) to the north, which are near completion and partially occupied; and Phase 3 (permitted under LCC Reg. Ref. 25/60386) to the south and east. Retention permission is sought for the re-orientation of 6 No. 4-bed houses (‘D’ house type) located along the northern boundary of the site, resulting in the front of the house now facing the internal street to the north; the relocation of the adjacent 4-bed house (‘B1’ house type) further west by approximately 2-metres; and minor amendments to hard and soft landscaping, boundary treatments, car parking and all other associated works above and below ground located adjacent to and within the curtilage of the 7 No. houses. No amendments have been made to the remaining 85 No. permitted residential units.
A c. 3.85 Ha site at Summerhill , Portlaoise , Co. Laois.
amend the residential development permitted under LCC Reg. Ref. 25/60385 at a c. 3.85 Ha site at Summerhill, Portlaoise, Co. Laois. This application relates to Phase 2 of the wider Sand Wood Development (generally bound by: the Southern Circular Road and Aghnaharna Drive to the north; the Holy Family Schools and Ashewood Walk to the east; and agricultural land to the south and west). The Phase 2 site is generally bound by: agricultural lands to the west; Phases 1A & 1B (permitted under LCC Reg. Refs. 23/60350 & 23/60348, as amended under LCC Reg. Ref. 25/60040) to the north, which are near completion and partially occupied; and Phase 3 (permitted under LCC Reg. Ref. 25/60386) to the south and east. The proposed amendments principally comprise: the replacement of 18 No. permitted two-storey 4-bed houses within the south-eastern extent of the site with 24 No. houses (19 No. three-storey 3-bed houses and 5 No. two-storey 4-bed houses), resulting in an increase of 6 No. houses; and the repositioning of 4 No. permitted two-storey 4-bed houses further north by approximately 1-metre to align with the front building line of the other permitted houses along the same street. The proposed amendments also comprise: new bicycle stores; amendments to the location and number of car parking (additional 12 No. spaces proposed); private amenity space; hard and soft landscaping; boundary treatments; and all associated works above and below ground.
A c. 3.85 Ha site at Summerhill , Portlaoise , Co. Laois.
make amendments to the residential development permitted under LCC Reg. Ref. 25/60385 at a c. 3.85 Ha site at Summerhill, Portlaoise, Co. Laois. This application relates to Phase 2 of the wider Sand Wood Development (generally bound by: the Southern Circular Road and Aghnaharna Drive to the north; the Holy Family Schools and Ashewood Walk to the east; and agricultural land to the south and west). The Phase 2 site is generally bound by: agricultural lands to the west; Phases 1A & 1B (permitted under LCC Reg. Refs. 23/60350 & 23/60348, as amended under LCC Reg. Ref. 25/60040) to the north, which are near completion and partially occupied; and Phase 3 (permitted under LCC Reg. Ref. 25/60386) to the south and east. The proposed amendments principally comprise: the replacement of 18 No. permitted two-storey 4-bed houses within the south-eastern extent of the site with 24 No. houses (19 No. three-storey 3-bed houses and 5 No. two-storey 4-bed houses), resulting in an increase of 6 No. houses; and the repositioning of 4 No. permitted two-storey 4-bed houses further north by approximately 1-metre to align with the front building line of the other permitted houses along the same street. The proposed amendments also comprise: new bicycle stores; amendments to the location and number of car parking (additional 12 No. spaces proposed); private amenity space; hard and soft landscaping; boundary treatments; and all associated works above and below ground.
A c. 3.85 Ha site at Summerhill , Portlaoise , Co. Laois.
retain amendments to 7 No. houses permitted as part of the residential development granted under LCC Reg. Ref. 25/60385 at a c. 3.85 Ha site at Summerhill, Portlaoise, Co. Laois. This application relates to Phase 2 of the wider Sand Wood Development (generally bound by: the Southern Circular Road and Aghnaharna Drive to the north; the Holy Family Schools and Ashewood Walk to the east; and agricultural land to the south and west). The Phase 2 site is generally bound by: agricultural lands to the west; Phases 1A & 1B (permitted under LCC Reg. Refs. 23/60350 & 23/60348, as amended under LCC Reg. Ref. 25/60040) to the north, which are near completion and partially occupied; and Phase 3 (permitted under LCC Reg. Ref. 25/60386) to the south and east. Retention permission is sought for the re-orientation of 6 No. 4-bed houses (‘D’ house type) located along the northern boundary of the site, resulting in the front of the house now facing the internal street to the north; the relocation of the adjacent 4-bed house (‘B1’ house type) further west by approximately 2-metres; and minor amendments to hard and soft landscaping, boundary treatments, car parking and all other associated works above and below ground located adjacent to and within the curtilage of the 7 No. houses. No amendments have been made to the remaining 85 No. permitted residential units.
A c. 3.85 Ha site at Summerhill , Portlaoise , Co. Laois.
The submission window has closed
Observations on this application closed on Wednesday 30 July 2025, five weeks after it was received. The authority cannot accept a late submission.