Nenagh North Nenagh South and Tyone , Abbeycourt Hotel Dublin Road , Nenagh
CONDITIONALPlanning application 2460449
Tipperary - Tipperary County Council
Proposed Development
(1) ground mounted solar PV panels with new fence enclosure and access gates; (2) a container battery storage installation with 6 electric vehicle charge points, and associated site works
View the full application file on the council's planning portal →Application Timeline
Application received
6 Jun 2024
Further information requested
30 Jul 2024
Further information received
7 Nov 2024
Decision due
4 Dec 2024
Decision: CONDITIONAL
4 Dec 2024
Grant issued
7 Jan 2025
Application Details
- Location
- Nenagh North Nenagh South and Tyone , Abbeycourt Hotel Dublin Road , Nenagh
- Applicant
- N/A
- Application Type
- PERMISSION
- Planning Authority
- Tipperary County Council
- Site Area
- 0.3 ha
Timeline
- Registration Date
- 6 June 2024
- Status
- APPLICATION FINALISED
- Decision
- CONDITIONAL
- Decision Date
- 4 December 2024
- Grant Date
- 7 January 2025
- Permission Expires
- 6 January 2030
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
1) ground mounted solar PV panels with new fence enclosure and access gates, 2) a switchgear container, 3) 6 No. electric vehicle charging points and associated site works
Nenagh North Nenagh South and Tyone , Abbeycourt Hotel Dublin Road , Nenagh
(1). Solar PV panels to the existing hotel roof (2). Two new wind turbines, not exceeding 21.2m height (3). A container battery storage installation with 6 electric vehicle charge points, weather monitoring station and associated site works
Nenagh North and Tyone , Abbeycourt Hotel Dublin Road , Nenagh
1. Solar PV panels to the existing hotel roof 2. Two new wind turbines, not exceeding 21.2m height. 3. A Container battery storage installation with 6 electric vehicle charge points, weather monitoring station and associated site works
Nenagh North and Tyone , Abbeycourt Hotel Dublin Road , Nenagh
one single storey free standing prefabricated building and associated external access steps and a ramp, within the grounds of the hotel, for the purposes of offering computed based examinations services to the public
The Great National Abbey Court Hotel , Dublin Road , Nenagh
the construction of 16 semi-detached, three-bedroom, 2-storey houses and 8 three-bedroom, two-storey terraced houses, 8 two-bedroom apartments over four storeys, new entrance gates and access road to existing holiday homes and associated site works
Tyone , Nenagh North & Nenagh South , Dublin Road Nenagh
the construction of 16 semi-detached, three-bedroom, 2-storey houses and 8 three-bedroom, two-storey terraced houses, 8 two-bedroom apartments over four storeys, new entrance gates and access road to existing holiday homes and associated site works
Castleway , Dublin Road , Nenagh
the construction of 16 semi-detached, three-bedroom, 2-storey houses and 8 three-bedroom, two-storey terraced houses, 8 two-bedroom apartments over four storeys, new entrance gates and access road to existing holiday homes and associated site works
Castleway , Dublin Road , Nenagh
construction of 16 semi-detached, three-bedroom, 2-storey houses and 8 three-bedroom, two-storey terraced houses, 8 two-bedroom apartments over four storeys, new entrance gates and access road to existing holiday homes and associated site works
Castleway , Dublin Road , Nenagh
(1) marque with base for the purpose of function / reception area, (2) canopy over external dining space
Abbey Court Hotel , Dublin Road Nenagh , Co Tipperary (Nenagh North / Tyone TLD)
material change of use of 10 existing three-storey holiday homes to private dwellings, including the construction of new metal railings to enclose front gardens, new bin stores, external landscaping, external lighting and associated site works
Tyone adjacent to the Abbey Court Hotel , Dublin Road , Nenagh Co. Tipperary