Castleway , Dublin Road , Nenagh
UNCONDITIONALPlanning application 24267
Tipperary - Tipperary County Council
Proposed Development
the construction of 16 semi-detached, three-bedroom, 2-storey houses and 8 three-bedroom, two-storey terraced houses, 8 two-bedroom apartments over four storeys, new entrance gates and access road to existing holiday homes and associated site works
View the full application file on the council's planning portal →Application Timeline
Application received
20 Nov 2024
Decision: UNCONDITIONAL
21 Jan 2025
Decision due
23 Jan 2025
Application Details
- Location
- Castleway , Dublin Road , Nenagh
- Applicant
- N/A
- Application Type
- EXTENSION OF DURATION
- Planning Authority
- Tipperary County Council
Timeline
- Registration Date
- 20 November 2024
- Status
- APPLICATION FINALISED
- Decision
- UNCONDITIONAL
- Decision Date
- 21 January 2025
- Permission Expires
- 9 February 2026
Location
Planning Applications Nearby
What the council has granted and refused around this site is the best guide to how a similar application will fare.
the construction of 16 semi-detached, three-bedroom, 2-storey houses and 8 three-bedroom, two-storey terraced houses, 8 two-bedroom apartments over four storeys, new entrance gates and access road to existing holiday homes and associated site works
Tyone , Nenagh North & Nenagh South , Dublin Road Nenagh
the construction of 16 semi-detached, three-bedroom, 2-storey houses and 8 three-bedroom, two-storey terraced houses, 8 two-bedroom apartments over four storeys, new entrance gates and access road to existing holiday homes and associated site works
Castleway , Dublin Road , Nenagh
construction of 16 semi-detached, three-bedroom, 2-storey houses and 8 three-bedroom, two-storey terraced houses, 8 two-bedroom apartments over four storeys, new entrance gates and access road to existing holiday homes and associated site works
Castleway , Dublin Road , Nenagh
material change of use of 10 existing three-storey holiday homes to private dwellings, including the construction of new metal railings to enclose front gardens, new bin stores, external landscaping, external lighting and associated site works
Tyone adjacent to the Abbey Court Hotel , Dublin Road , Nenagh Co. Tipperary
material change of use of 10 existing three-storey holiday homes to private dwellings, including the construction of new metal railings to enclose front gardens, new bin stores, external landscaping, external lighting and associated site works
Tyone adjacent to the Abbey Court Hotel , Dublin Road , Nenagh Co. Tipperary
1) ground mounted solar PV panels with new fence enclosure and access gates, 2) a switchgear container, 3) 6 No. electric vehicle charging points and associated site works
Nenagh North Nenagh South and Tyone , Abbeycourt Hotel Dublin Road , Nenagh
(1) ground mounted solar PV panels with new fence enclosure and access gates; (2) a container battery storage installation with 6 electric vehicle charge points, and associated site works
Nenagh North Nenagh South and Tyone , Abbeycourt Hotel Dublin Road , Nenagh
(1). Solar PV panels to the existing hotel roof (2). Two new wind turbines, not exceeding 21.2m height (3). A container battery storage installation with 6 electric vehicle charge points, weather monitoring station and associated site works
Nenagh North and Tyone , Abbeycourt Hotel Dublin Road , Nenagh
the construction of 16 semi-detached, three-bedroom, 2-storey houses and 8 three-bedroom, two-storey terraced houses, 12 two-bedroom apartments over four storeys, new entrance gates and access road to existing holiday homes and associated site works
Tyone , Nenagh North & Nenagh South , Dublin Road
1. Solar PV panels to the existing hotel roof 2. Two new wind turbines, not exceeding 21.2m height. 3. A Container battery storage installation with 6 electric vehicle charge points, weather monitoring station and associated site works
Nenagh North and Tyone , Abbeycourt Hotel Dublin Road , Nenagh
Planning a project of your own?
Find out in two minutes whether you need planning permission. It's free, and based on the exempted development regulations.
Do I Need Permission?